# Nebius Can Sell the Next Rack Before It Pays for It

When an AI customer wants scarce compute badly enough, it will put cash down before the machines arrive. Nebius says prepayments on contracts signed in the September quarter covered **more than 100% of the capital expenditure associated with those deals**, up from 50–60% for the June cohort. A customer renewing capacity already installed can provide cash for the next build, even though Nebius has already paid for the rack that customer will use. The customer gets a reservation; the operator gets time. [November 12 shareholder letter, “Customers” and “Capital requirements”](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-2.htm).

Time, rather than the absence of demand, is the financing issue. In the same quarter Nebius generated $980.8m of consolidated revenue and used $273.0m of operating cash. It paid $7.3004bn for property, equipment and intangibles. Both stories can be true: a particularly attractive set of contracts can fund its own hardware while the wider company is still writing cheques for other customers, sites and future capacity. [Quarterly results and cash-flow statement](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-1.htm).

![How customer advances, receivables and investment cash flows connect to the 2027 funding plan.](/downloads/november-nebius/funding-clocks.svg)

## The bargain behind the advance

More than 90% of the **value of contracts signed in Q3** carried a prepayment, according to management. Read that sentence from the customer's side. An advance buys priority and commits part of a future budget; the customer is taking some delivery exposure today for a better claim on tomorrow's compute. From Nebius's side, that cash can reduce the need to borrow while a site is being built. The cost shows up in what the customer negotiates in return: capacity, duration, price and service terms. A 90% share of contracts *with* an advance can coexist with a much smaller fraction of contract value actually prepaid. [Shareholder letter](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-2.htm).

An early deposit and a loan against the remaining contract can complement one another if the lender underwrites the receipts that are still to come. They can also compete for the same future dollar. A buyer that paid part of the price upfront will eventually take service against that payment; a lender cannot collect the same dollar again. For a project team the practical negotiation is therefore over the remaining billed cash, delivery milestones and lenders' access to it, as much as over the opening deposit.

## The cash statement tells the other half of the story

For the September quarter, the **deferred-revenue adjustment contributed $3.434bn** to operating cash flow. The **receivables adjustment absorbed $3.762bn**. Together the two lines consumed $327.8m. The rest of operating cash flow added back $54.8m, leaving the group at **negative $273m**. These are net working-capital adjustments; the company does not assign them to exactly the same customers. The detailed accounts put ending deferred revenue at **$9.4092bn**, including amounts that may be refundable, primarily under strategic customer agreements. That balance is the value of service still owed on cash already received, subject to the contract terms. [Detailed financial statements, deferred-revenue note](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126238/nbis-ex99d2.htm).

| Consolidated Q3 cash bridge | USD billions |
| --- | ---: |
| Opening cash and equivalents, including restricted cash | 9.0981 |
| Operating cash | −0.2730 |
| Investing cash | −7.6352 |
| Financing cash | +7.4576 |
| Foreign-exchange effect | −0.0064 |
| **Closing cash and equivalents, including restricted cash** | **8.6411** |

The quiet line in that bridge is financing. Nebius received $5.75bn from issuing convertible notes in the quarter, before issuance costs, as well as $773.3m of long-term debt proceeds. The $2bn received from its pre-funded equity warrant appears in the **nine-month** column; the quarter itself records zero. Of the closing $8.6411bn, $1.2155bn was restricted, leaving $7.4256bn in the cash-and-equivalents caption. The dates matter: the October Citi bridge came **after** this balance sheet. [Cash-flow statement and reconciliation](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-1.htm).

## Two loans buy different kinds of time

In July, Nebius financed deployed GPUs and contracted cash flows from an investment-grade customer. The November 12 detailed filing puts the loan at **$773.3m**, versus approximately $775m in the earlier disclosure. Two operating subsidiaries are the borrowers; lenders have security over substantially all of their assets, with specified exceptions. The facility has a **1.15× minimum debt-service coverage ratio**, a minimum-liquidity test and monthly amortization that began August 15. The parent provided specified bad-act and performance guarantees. The price: one-month Term SOFR plus **2.50 percentage points**, with hedging requirements, to an October 2030 maturity. The underwriter had both an operating asset and a customer contract to inspect. [Earlier facility description](https://www.sec.gov/Archives/edgar/data/1513845/000110465926094844/nbis-20260812xex99d2.htm) · [Detailed terms, Note 12](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126238/nbis-ex99d2.htm).

The **$3.5bn Citi bridge** serves a different job: it gives the group a borrowing route while infrastructure investment runs ahead of longer-term funding. The parent is itself a borrower. The facility takes a broad security interest in borrower assets, subject to exceptions, and matures October 16, 2027. Its starting margin of **2.75 points** steps up by 0.25 points every 90 days to 3.50 points, subject to adjustments. The rising margin gives Nebius an incentive to replace bridge money once longer-duration customer-backed financing is ready. The October 22 filing dates the agreement October 17; the November subsequent-events note uses October 22. Under either account, both facilities predate the November 11 NVIDIA board action. Their different prices are more instructive about collateral and tenor than about succession. [Transaction 6-K](https://www.sec.gov/Archives/edgar/data/1513845/000110465926117978/tm2628078d1_6k.htm) · [Subsequent events, Note 16](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126238/nbis-ex99d2.htm).

## How much of 2027 is left to fund?

Management expects customer prepayments **plus** asset-backed borrowing against existing investment-grade customer contracts to cover **75–85% of $40–45bn in 2027 capex**. At a $42.5bn illustrative midpoint and 80% coverage, that's **$34bn** from those two sources and **$8.5bn** from elsewhere. A shift of five percentage points in coverage moves the other-funding requirement by **$2.125bn** at that capex level. That is why a few points of advance funding can matter more than a few basis points of spread. [Funding guidance](https://www.sec.gov/Archives/edgar/data/1513845/000110465926126008/tm2629571d1_ex99-2.htm).

| 2027 capex | Combined funding share | Prepayments + asset financing | Other sources |
| ---: | ---: | ---: | ---: |
| $40bn | 75% | $30bn | $10bn |
| $40bn | 85% | $34bn | $6bn |
| $45bn | 75% | $33.75bn | $11.25bn |
| $45bn | 85% | $38.25bn | $6.75bn |

Management also expects $17–20bn of **committed** customer prepayments in 2027. That is one component of the plan. The arithmetic above describes funding mix, not a forecast stock offering. Retained cash, operating receipts, debt and equity are different ways to meet the remainder. In a given month, even a fully financed annual plan can need a bridge if an equipment invoice lands ahead of its customer advance.

The investment case turns on that sequence. A signed customer can reserve scarce compute and help finance the asset it wants. After delivery, the contractual receipts and the machines themselves can support a longer loan; that loan can free capital for the next site. Watch for **dated customer cash, actual borrowing against eligible contracts, and equipment accepted on schedule**. If those three arrive in order, a neocloud can compound capacity without returning to the equity market for every new rack. If they arrive out of order, the cost of time shows up in the bridge.

[Download the four-corner model](/downloads/november-nebius/Nebius-Funding-Window-2026-11-12.zip) · [Open the November 12 research card](/downloads/november-nebius/reader-card.html) · [Model inputs](/downloads/november-nebius/evidence.json) · [Results](/downloads/november-nebius/results.json).