# Oracle Raised $20 Billion. Its Bonds Won’t Wait for the Power.

On **February 4, 2027**, Oracle Corporation is scheduled to pay **$50 million** of interest on one of the five bonds it issued on November 4. The payment falls due whether a new data center is selling compute that morning or still waiting for power. That is the bargain in Oracle’s $20bn equity-and-debt raise: borrow on the strength of the whole company to get construction moving, and leave the company responsible for the time between spending the money and collecting from the customer. [Closing 8-K](https://www.sec.gov/Archives/edgar/data/1341439/000119312526447507/d131790d8k.htm) · [Note terms](https://www.sec.gov/Archives/edgar/data/1341439/000119312526445846/d181336d424b2.htm)

The claims on Oracle are clear. Bondholders bought five dated streams of interest and principal; new shareholders bought a lasting share of the company’s economics. The package raised **$19.836bn after underwriting discounts and before other issuer expenses**. How far it carries the buildout depends on the length of the interval before customers start paying, not just the amount raised.

## Equity buys time and sells a piece of the upside

![Common-share issuance and note proceeds: from roughly $20bn headline to $19.836bn before other expenses.](/downloads/november-oracle/capital-and-dilution.svg)

Oracle issued **86,206,897 common shares at $116**, along with **$10bn face value of notes**. The equity brought in $9.8785bn after underwriting; the notes brought in $9.9573bn on the same basis. The notes’ offering price was $8.9275m below par and underwriting discounts across both issues totaled $155.25m. Estimated issuer expenses would reduce the combined figure to about $19.826bn before an unspecified reimbursement. [Equity prospectus](https://www.sec.gov/Archives/edgar/data/1341439/000119312526445847/d181425d424b5.htm) · [Debt prospectus](https://www.sec.gov/Archives/edgar/data/1341439/000119312526445846/d181336d424b2.htm)

Consider an existing shareholder who owns 1% and buys none of the new shares. On the prospectus’s August 31 share base, Oracle’s share count rises **2.851%**. The holder ends up with about **0.9723%** of the pro forma company—a **2.772% relative reduction** in ownership. The future return on the new capital now matters to both sets of shareholders. The **11.227% discount** between $116 and the October 30 reference close of $130.67 is a different price paid to place the issue. It describes entry price, not the holder’s change in ownership.

That exchange is particularly valuable in a construction cycle. Equity investors can wait through a commissioning delay without receiving a scheduled principal payment. In return, they keep their claim long after the site is producing cash. Bondholders take a fixed coupon and a maturity date. They do not take on the same wait.

## Corporate interest starts before a site has to earn it

![First 2027 coupon dates and amounts, the normal annual coupon and five maturities.](/downloads/november-oracle/coupon-and-maturity.svg)

| Question for treasury | Scheduled interest on the new notes |
|---|---:|
| What is due by May 31, the end of Oracle’s FY2027? | $338.375m |
| What is due in calendar 2027? | $726.750m |
| What is a normal full year while all five tranches are outstanding? | $776.750m |

The difference comes down to the first coupon on the $2.5bn 2037 tranche. It accrues just three months from November 4, 2026 to February 4, 2027: 8% on a 30/360 convention produces **$50m**. Its August coupon covers a full half year and is **$100m**. The other four first coupons fall on May 4. A budget that drops the full annual run rate into FY2027 would overstate that fiscal year’s scheduled coupon cash by **$438.375m**. [Payment and day-count terms](https://www.sec.gov/Archives/edgar/data/1341439/000119312526445846/d181336d424b2.htm)

Across all tranches, the face-weighted coupon is **7.7675%**. Oracle Corporation is the sole obligor; the senior unsecured notes have no subsidiary guarantee. The advantage for a project sponsor is access to corporate funding before the site has its own operating receipts. The price is that a late site competes with the rest of the business for cash to service the parent’s debt. Bond maturity is spread from 2029 to 2046; the first interest payment arrives much sooner.

## How much more could Oracle borrow?

![Oracle's capital-market plan, separate financing instruments and the project delivery calendar.](/downloads/november-oracle/capital-versus-delivery.svg)

At Investor Day on October 28, Oracle described $20bn of additional capital-market financing through FY30: $10bn of equity and $10bn of gross debt, **excluding refinancing**. The November closings match that split. A separate $20bn at-the-market share program had already been used in FY27 Q1. Its $19.909bn of net proceeds were in the August-quarter cash statement. So was an $11.363bn customer-prepayment adjustment, already inside operating cash flow. Those earlier receipts belong to an earlier cash balance. [Investor Day announcement](https://investor.oracle.com/investor-news/news-details/2026/Oracle-Investor-Day-2026-Accelerating-Value-Creation/default.aspx) · [August-quarter filing](https://www.sec.gov/Archives/edgar/data/1341439/000119312526389274/orcl-20260831.htm)

A lender asking what Oracle can still borrow needs three different answers. The capital-market plan describes **management’s intended issuance**. The $10bn revolving credit facility describes **committed bank capacity subject to conditions**: it had no borrowings at May 31 and carries a defined interest-coverage covenant of at least 3.0×. The $10bn commercial-paper program describes **authorized market issuance**: $1.5bn was outstanding at May 31, and new placements require buyers. The new notes place no cap on additional unsecured borrowings and carry no financial covenant of their own. For November borrowing room, the decisive data are current facility usage, covenant headroom and the price at which investors will actually buy. [FY2026 10-K, Note 5](https://www.sec.gov/Archives/edgar/data/1341439/000119312526277521/orcl-20260531.htm) · [Note indenture summary](https://www.sec.gov/Archives/edgar/data/1341439/000119312526445846/d181336d424b2.htm)

## At Project Jupiter, the scarce asset was time

New Mexico’s State Land Office described a July 14 rejection of a request to reconsider a pipeline route across state land. State environmental records separately identify Project Jupiter’s air-permit application 10883 and docket AQB 26-57(P). These are the kinds of dependencies a capital raise cannot move onto a financing timetable. [State Land Office decision account](https://www.nmstatelands.org/2026/07/15/commissioner-garcia-richard-again-denies-request-to-run-portion-of-project-jupiter-pipeline-through-state-lands/) · [Environmental notices](https://www.env.nm.gov/public-notices/) · [Docket index](https://www.env.nm.gov/opf/docketed-matters/)

On September 24, Reuters reported that Oracle invoked force majeure over power delays, seeking to shift project payment timing; the report also quoted Blue Owl as saying financial commitments remained unchanged. That distinction matters to both sides. If a valid notice pushes a project payment out, the tenant gains time and the party expecting payment needs a longer bridge. If the payment still falls due, the tenant finances the interval until usable capacity produces receipts. The private notice and lease would determine the outcome. The corporate noteholders have their own contract either way. [Reuters reporting](https://www.streetinsider.com/Reuters/Oracle%2Btriggers%2Bforce%2Bmajeure%2Bon%2Bdata%2Bcenter%2Bproject%2Bover%2Bpower%2Bdelays%2C%2Bsource%2Bsays/27099446.html?classic=1)

**What Oracle bought was financing time, not electricity.** Combining equity with corporate debt lets it fund work while power, equipment and customer acceptance catch up. For the next funding decision, compare unrestricted cash and available bank capacity with the *next* construction and coupon dates; then ask which sites will deliver cash before those dates. A new acceptance milestone or a signed change in lease payments can move that calculation as much as another capital raise.

[Download the research kit](/downloads/november-oracle/research-kit.zip) · [Source and assumptions ledger](/downloads/november-oracle/evidence.json) · [91-row contractual schedule](/downloads/november-oracle/results.json) · [Calculator](/downloads/november-oracle/calculate.mjs) · [Checks](/downloads/november-oracle/verify.mjs) · [Figure generator](/downloads/november-oracle/render-figures.mjs)

*The schedule uses contractual dates before business-day adjustments and assumes no early retirement. Issuance spreads, coupons and Treasury adjustments in early-redemption formulas serve different purposes.*